[WATER OUR FOCUS]

North Nowra Surcharge Main Upgrade

Replacing critical sewer rising main infrastructure beneath the Nowra Bridge as part of the Princes Highway upgrade.
Transport for NSW / Nowra Bridge Upgrade Program
Nowra, New South Wales

Nowra, New South Wales

[Project Background]

Critical Sewer Infrastructure Upgrade within Major Bridge Project

As part of the Princes Highway Nowra Bridge upgrade, significant infrastructure works were undertaken to improve transport connectivity across the Shoalhaven River. The project included the construction of a new four-lane bridge and repurposing of the existing bridge structures.

To support these works, the North Nowra Surcharge Sewer Main installed beneath the original bridge in 1981 required replacement. Killard was engaged to deliver the upgrade and installation of the new rising main infrastructure while maintaining safe operations within the bridge construction environment.

[Scope Of Works]
Operating in Sensitive and Live environments

Replacement of ageing surcharge mains infrastructure supporting the Princes Highway bridge upgrade project.

Installation of DN300 DICL and OD560 HDPE sewer pipelines
Construction of 350m OD505 steel surcharge main beneath the existing bridge structure
Removal and disposal of existing asbestos sewer infrastructure
Connection and commissioning of new sewer mains within the live network
Project Technical Snapshot

Replacement of aging sewer surcharge infrastructure across the Nowra Bridge corridor.

350m Steel Sewer Rising Main
350m Steel Sewer Rising Main
Pipe Materials
DN300 DICL · OD560 HDPE · OD505 Steel
Bridge Installation
Pipeline installation beneath the existing bridge structure
[Outcome / Key Features]
Enabling Works for Pump Station Replacement
Outcome
  • Installation of 350 metres of OD505 steel sewer rising main beneath the existing Nowra Bridge
  • Installation of additional DN300 DICL and OD560 HDPE pipelines within the network upgrade
  • Integration and connection to the North Nowra surcharge sewer network
  • Removal and off-site disposal of existing asbestos cement mains
Key Features
  • Innovative installation methodology developed for pipeline installation over water
  • Bridge-mounted scaffolding and bridge-specific elevated work platforms (EWP) used for construction
  • Specialised engineered brackets and rollers used to guide the pipe across the bridge span
  • Winch systems and fabricated steel cone used to safely manoeuvre pipe sections during installation
  • Custom expansion joints designed to accommodate bridge movement due to temperature changes
  • Removal of existing asbestos pipeline using floating barges, EWP and spider crane
[Environmental Responsibility]
Managing construction within a river crossing environment
Construction activities were carefully managed to minimise impacts on the surrounding river environment and bridge operations. Controlled installation procedures and safe removal of the existing asbestos pipeline ensured the surrounding waterways and infrastructure were protected throughout the works.
No items found.
Partner With a Specialist in Critical
Water Infrastructure
If your project demands certainty, compliance, and disciplined delivery within live water networks, we’re ready to engage.
Contact Us
Contact Us