[WATER OUR FOCUS]

Five Dock BaptistCare Utilities Infrastructure

Delivering multi-utility upgrades and connections to support affordable housing development in Five Dock.
BaptistCare Affordable Housing Program – Lendlease
Five Dock, New South Wales

Civil & Multi-Service Works

[Project Background]

Utility Infrastructure for Affordable Housing Development

As part of a NSW Government initiative to deliver affordable housing across several sites, BaptistCare engaged Lendlease Building to design and construct residential developments including the Five Dock site within the Canada Bay Council area.

To service the new apartment buildings, upgrades and connections to existing potable water, stormwater and high-voltage electrical infrastructure were required along Kings Road and Great North Road.

[Scope Of Works]
Operating in Sensitive and Live environments

Construction of utility infrastructure supporting affordable housing development in Five Dock.

Installation of high-voltage electrical infrastructure and associated substation connections
Construction of stormwater and potable water main infrastructure
Relocation of power poles and existing utility services
Pavement, kerb, gutter, and footpath reinstatement works
Project Technical Snapshot

Installation and upgrade of urban utility infrastructure to support new residential development.

150m High Voltage Electrical Connection
150m High Voltage Electrical Connection
Stormwater Infrastructure Installed
90m DN375 Stormwater Pipeline
Water Infrastructure Installed
120m DN150 DICL Water Main
[Outcome / Key Features]
Urban Utility Connections Delivered
Outcome
  • Installation of high voltage electrical infrastructure connecting to a new on-site substation
  • Construction of DN375 stormwater pipeline infrastructure along Kings Road
  • Installation of DN150 ductile iron potable water main connecting to existing trunk infrastructure
  • Pavement restoration including asphalt, kerb, gutter and footpath reinstatement
Key Features
  • Relocation of three power poles with multiple service providers including Ausgrid, Telstra, Optus and Foxtel
  • Night works implemented to minimise disruption to traffic along major road corridors
  • Extensive potholing investigations to confirm underground service locations prior to excavation
  • Complex utility connections undertaken within a TfNSW road intersection
  • Coordination with Canada Bay Council, RMS, Ausgrid and Sydney Water throughout project delivery
  • Final reinstatement completed to authority standards
[Environmental Responsibility]
No items found.