Wingecarribee Shire Council embarked on a program of water main renewals in response to the blow outs of existing mains. The entire program runs for two years with the option of a further two years.
This project within the program consisted of replacing a 375mm cast iron water main on the Illawarra Highway at Sutton Forest, which was considered critical infrastructure.
KILLARDS PORTFOLIO
WSC Sutton Forest Trunk Main
Project Introduction
Project Details
Client
Wingecarribee Shire Council
Project dates
May 2020 to July 2020
Discipline
Cast iron water main renewals
Asset Owner
Wingecarribee Shire Council
Location
Wingecarribee Shire
Scope of Works
Original plan for replacement was to pipe burst the existing line however due to the shallow depth (risk of heaving) and proximity to a TfNSW road, the decision was made to use a combination of open cut and directional drilling.
Project features
- 2 x22t, 1x17t, 1x13t and 2x5t t Excavators, Non-Destructive Digging truck, 8t Tipper, 2 x Skip truck
- DN500 x 2.8km. Pipe material HDPE